TakeOff report, where does the following come from

In the TakeOff report for Item code there is a “0.0”, where does that come from.

See below images:

Where does this come from.JPG

BIM attributes.JPG

Hi JClements,

The 0.0 in the take off that your talking about is for the price of labour that can be changed and adjusted using :bim-tool: . (Labour (AUD))
forum post 1.png

Here I have set the price of labour as 75. Now when I do a take off with the product inside my model I get 75 instead of 0.0
forum post 1-2.png

If you have any other problems just let us know.

Kind Regards
Dean

Thanks for your quick response